Cost/Cost: Accrues revenue and bills using the ratio of actual cost to budgeted cost (percent complete)
Cost/Event: Accrues revenue using the ratio of actual cost to budgeted cost (percent complete) and bills based on events
Cost/Work: Accrues revenue using the ratio of actual cost to budgeted cost (percent complete) and bills as work occurs
Event/Event: Accrues revenue and bills based on events
Event/Work: Accrues revenue based on events and bills as work occurs
Work/Event: Accrues revenue as work occurs and bills based on events
Work/Work: Accrues revenue and bills as work occurs
-----------------------------------------------------------------
Cost: POC calculation, Automatic creation
Work: Total work, Automatic creation
Event: Manual creation
POC Revenue = Actual Cost / Budgeted Cost X Budgeted Revenue
Cost/Event: Accrues revenue using the ratio of actual cost to budgeted cost (percent complete) and bills based on events
Cost/Work: Accrues revenue using the ratio of actual cost to budgeted cost (percent complete) and bills as work occurs
Event/Event: Accrues revenue and bills based on events
Event/Work: Accrues revenue based on events and bills as work occurs
Work/Event: Accrues revenue as work occurs and bills based on events
Work/Work: Accrues revenue and bills as work occurs
-----------------------------------------------------------------
Cost: POC calculation, Automatic creation
Work: Total work, Automatic creation
Event: Manual creation
POC Revenue = Actual Cost / Budgeted Cost X Budgeted Revenue